Zoning Approved: 06/24/2020
Civil Plan Submitted to City: December 2020
Civil Plan Approval by City: March 2021**
Infrastructure Development done: July 2021
Vertical Construction Phase 1 Start: August 2021
Vertical Construction Phase 2 Start: February 2022*
Vertical Construction Phase 3 Start: August 2022*
Vertical Construction Phase 4 Start: February 2023*
Final Phase: May 2023


*Dates are tentative
**Subject to city approval of construction permits